S. Giuliano Park bicycle/pedestrian path

Task

Cable-stayed bicycle/pedestrian path

  • Location

    Mestre (VE)

  • Designer

    Arch. Di Mambro

  • Client

    Contractor: Impresa di Costruzioni Ing. E. Mantovani S.p.A.

  • Date

    2004

  • Technical Characteristics

    The 140 m long footbridge has two access ramps to the north and south, of 112 m and 73 m respectively. The deck forming the framework of the bridge is anchored to two reinforced concrete abutments at its ends, and is supported by pre-stressed stays, anchored to a steel column placed exactly at the central point of the structure, stabilised by special transverse tie rods. The structure is constructed of two box beams, placed laterally to connecting struts, which support longitudinal profiles on which the treated wood plank flooring is laid. The stabilising horizontal bracing is provided by diagonal bars. The stays are anchored to the outside of the lateral beams by means of stringer heads at the top of the columns