Sir3, the most challenging construction site begins. Starting Monday the 13th, the two embankments on the Scaricatore side will be closed for a year. The new steel bridge for trams, cyclists, and pedestrians will be installed in May. Councilor Ragona: “This is the most challenging and impactful part of the Sir3 construction site.”
The new 820-ton steel bridge, built by MBM of Verona, among other companies, will be similar to the existing one, but larger: 100 meters long. It will take about 20 days to move the bridge over the canal in early summer.