Two Arch Bridges

Task

Construction of the Volano and Baccarini bridges. Tubular section arch

  • Location

    Codigoro (FE)

  • Designer

    Eng. Mario Organte

  • Client

    Contractor: Alissa

  • Date

    2006

  • Technical Characteristics

    Maximum span 70 m. The Baccarini Bridge was launched by assembling the entire deck structure, arch, tension bars and upper bracing on steel sleds; it was then launched from the embankment to the opposite abutment. The nose usually installed for this type of launching was not necessary because the structure, having arrived about halfway up the river, was supported by a crane and accompanied to the supporting abutment. For launching, temporary struts were mounted transversely to the tension bars